문제1
You are the Test Manager of a new project aimed at developing a software system that must be certified at level B of the DO-178B standard. The project will follow a V-Model software development life cycle and it will have four formal levels of testing: component, integration, system and acceptance testing.
You must produce the test plan documentation for this project by providing an adequate coordination across the four levels of testing in order to assure auditability.
Which of the following answers would you expect to best describe how to organize the test plan?
Number of correct responses: 1

정답: C
문제2
The following are the requirements identified as "critical":
REQ-SEL-001. The user shall be able to combine all the three products with all the four durations to define an item to purchase
REQ-SEL-002. The user shall be able to add a maximum of six different items to the shopping cart
REQ-PUR-001. The user shall be able to purchase all the items in the shopping cart using a credit voucher
REQ-PUR-002. The user shall be able to purchase all the items in the shopping cart using the available credit already charged on the smartcard
REQ-PUR-003. The user shall be able to purchase all the items in the shopping cart using all the accepted credit cards
(Visa, MasterCard and Great Wall Card)
REG-LOGO-001. The user shall be able to logout (by clicking the logout button) from both the "select" and "purchase" pages going back to the "browse" page (anonymous navigation)
Moreover the following quality risk item has been identified as "critical":
QR-P1. The web customer portal might not be able to provide the expected response time (less than 10 sec) for the purchase transactions under a load of up-to 1000 concurrent users
Test analysis for system testing has just begun and the following test conditions have been identified:
TC-SEL-01. Test the combinations of products and durations to define an item to purchase
TC-SEL-02. Test the maximum number of items, which can be added to the shopping cart
TC-PUR-01. Test the purchase of an item
TC-PUR-02. Test the purchase of an item with the credit charged on the smartcard
What is the MINIMUM number of test conditions that must be added to fulfill both the EXCR1 and EXCR2 exit criteria?
Number of correct responses: 1

정답: A
문제3
The following is the unique "critical" quality risk item that has been identified:
CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to get the number of bottles from the user
Test analysis for system testing has just begun and the following test conditions have been identified:
TC-SEL-2. Test the selection of the package sizes
TC-SEL-4. Test wrong numbers of bottles for an order
TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles from the user
What is the MINIMUM number of test conditions that must be added to fulfill both the EXCR1 and EXCR2 exit criteria?
Number of correct responses: 1

정답: B
문제4
Consider the following test strategies:
I. Consultative test strategy
II. Reactive test strategy
III. Analytical test strategy
IV. Process-compliant test strategy
Consider also the following examples of test activities:
1. Prioritize the test cases, based on the results of a FMEA analysis, to ensure early coverage of the most important areas and discovery of the most important defects during test execution
2. Execute usability testing driven by the guidance of a sample of users (external to the test team)
3. Perform exploratory testing sessions throughout the system test phase
4. On an Agile project, execute tests that cover the test conditions identified for each user story of a feature planned for an iteration
Which of the following correctly matches each test strategy with an appropriate example?
Number of correct responses: 1

정답: D
문제5
Assume you are managing a test automation project for a mission-critical system.
Because vendor provided tools and open source solutions don't meet the needs of this project, you ask your test team to develop a custom automation framework.
Which of the following management issues associated to the development of this custom automation framework is least likely to manage?
Number of correct responses: 1

정답: D
문제6
You can count on well-written requirements, but you can't count on an adequate contribution of the stakeholders to the quality risk analysis. You have to mitigate the insufficient contribution of the stakeholders because the risk-based testing approach shall minimize the product risks. Your test team has one expert tester in security testing.
Which of the following test activities would you expect to be the less important in this context?
Number of correct responses: 1

정답: A
문제7
In the test strategy document your organization declares:
-to adopt a V-model development lifecycle, with three formal levels of testing: unit, integration and system testing
-to use a blended risk-based and regression-averse testing strategy for each level of testing
The following is an excerpt of the "approach" section for the system test plan document of a new project:
"Testing will only use manual tests. Due to the short period of time for test execution, the following activities will be performed in parallel with test execution: Test planning, test analysis and test design.
Basic metrics will be taken for test effort (i.e. person-hours), test cases executed (passed/failed), and incidents (no more metrics, such as code coverage, will be collected)."
In the system test plan, no deviations from the test strategy are described.
Based only on the given information, which of the following statements is true?
Number of correct responses: 1

정답: C

KoreaDumps의 제품으로 GO GO GO !

자격증의 중요성:

경쟁율이 심한 IT시대에 인증시험을 패스함으로 IT업계 관련 직종에 종사하고자 하는 분들에게는 아주 큰 가산점이 될수 있고 자신만의 위치를 보장할수 있으며 더욱이는 한층 업된 삶을 누릴수 있을수도 있습니다.

KoreaDumps 제품의 가치:

KoreaDumps에는 IT인증시험의 최신 학습가이드가 있습니다. KoreaDumps의 IT전문가들이 자신만의 경험과 끊임없는 노력으로 최고의 학습자료를 작성해 여러분들이 시험에서 패스하도록 도와드립니다.

무료샘플 받아보기:

관심있는 인증시험과목 덤프의 무료샘플을 원하신다면 덤프구매사이트의 PDF Version Demo 버튼을 클릭하고 메일주소를 입력하시면 바로 다운받아 덤프의 일부분 문제를 체험해 보실수 있습니다.

완벽한 서비스 제공:

KoreaDumps는 한국어로 온라인상담과 메일상담을 받습니다. 덤프구매후 일년동안 무료 업데이트 서비스를 제공해드리며 구매일로 부터 60일내에 시험에서 떨어지는 경우 덤프비용 전액을 환불해드려 고객님의 부담을 덜어드립니다.