최신Oracle Project Portfolio Management Cloud 2018 Implementation Essentials - 1Z1-1008무료샘플문제
문제1
Your customer complains that their project resources do not report their time promptly, which has resulted in incorrect reporting of project performance. What should you do to fix this problem? (Choose the best answer.)
Your customer complains that their project resources do not report their time promptly, which has resulted in incorrect reporting of project performance. What should you do to fix this problem? (Choose the best answer.)
정답: A
문제2
Which four notification templates are predefined?
Which four notification templates are predefined?
정답: B,C,D,E
설명: (KoreaDumps 회원만 볼 수 있음)
문제3
Your customer wants to see how quantity, cost, and revenue amounts are automatically distributed by using Spread Curve. Identify two period options that are available for this purpose. (Choose two.)
Your customer wants to see how quantity, cost, and revenue amounts are automatically distributed by using Spread Curve. Identify two period options that are available for this purpose. (Choose two.)
정답: A,C
설명: (KoreaDumps 회원만 볼 수 있음)
문제4
Your customer accounts revenuebased on,product class category. Because all your customer's projects are funded by private and government institutions, they decide to classify all projects based on their funding source to accurately report on revenue in General Ledger. Accordingly, you create a new class category
"Funding Source" and assign it to all projects. However, you notice that the accounting is still happening based on product class category.Identify the reason for this problem. (Choose the best answer.)
Your customer accounts revenuebased on,product class category. Because all your customer's projects are funded by private and government institutions, they decide to classify all projects based on their funding source to accurately report on revenue in General Ledger. Accordingly, you create a new class category
"Funding Source" and assign it to all projects. However, you notice that the accounting is still happening based on product class category.Identify the reason for this problem. (Choose the best answer.)
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)
문제5
Using Oracle Time and Labor, your client wants to put in a validation process that allows only a certain number of maximum hours an employee can charge in a day, and a minimum of hours he or she can report in a week.
What feature would you use to meet this requirement? (Choose the best answer.)
Using Oracle Time and Labor, your client wants to put in a validation process that allows only a certain number of maximum hours an employee can charge in a day, and a minimum of hours he or she can report in a week.
What feature would you use to meet this requirement? (Choose the best answer.)
정답: C
문제6
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets basedon the construction-in-process cost of each asset.Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement. (Choose the best answer.)
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets basedon the construction-in-process cost of each asset.Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement. (Choose the best answer.)
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)
문제7
Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this.(Choose the best answer.)
Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this.(Choose the best answer.)
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)
문제8
Which two statements are true about a project in "Draft" status? (Choose two.)
Which two statements are true about a project in "Draft" status? (Choose two.)
정답: A,B
설명: (KoreaDumps 회원만 볼 수 있음)
문제9
Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the resources at project level, forecasts are regenerated. After reviewing the cost amounts associated with the resources, you suspect that the cost association does not match your client's expectations.Identify two valid rules based on which cost association works. (Choose two.)
Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the resources at project level, forecasts are regenerated. After reviewing the cost amounts associated with the resources, you suspect that the cost association does not match your client's expectations.Identify two valid rules based on which cost association works. (Choose two.)
정답: A,C
설명: (KoreaDumps 회원만 볼 수 있음)
문제10
You have a billable project for which the following details are provided:
Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
Associated Project Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)
You have a billable project for which the following details are provided:
Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
Associated Project Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)