문제1
Your organization has been awarded a new contract based on which you are allowed to sell:
* Items not tracked in inventory
* Inventory items
* Services
Which contract structure would fulfill your requirement of item sales? (Choose the best answer.)

정답: A
문제2
What are three configuration items that you need to set up by using the Project Organizations functional area in Project Financial Management configurations? (Choose three.)

정답: A,B,E
설명: (KoreaDumps 회원만 볼 수 있음)
문제3
Which three features are part of Oracle Fusion Functional Setup Manager?

정답: A,D,E
설명: (KoreaDumps 회원만 볼 수 있음)
문제4
Your customer wants to assign the Net 45 payment term to all sets except for the corporate business unit specific set, which is assigned the Net 15 payment term. At transaction entry, the list of values for payment terms consists of only one set of data: the set that is assigned to the transaction's business unit.
Which reference data sharing method would you set up to meet the customer requirement? (Choose the best answer.)

정답: B
문제5
You are now the project manager of a newly created implementation project. Which two items are not part of managing an implementation project?

정답: A,D
문제6
You are trying to create a project purchase order (PO) but you are unable to select Expenditure Organization in the PO. Identify two reasons for this problem. (Choose two.)

정답: B,D
설명: (KoreaDumps 회원만 볼 수 있음)
문제7
You search for resources to fulfill a project resource request but are unable to proceed after receiving the following error message: "The search for resources cannot be completed because the project resource search index is not available. Contact your help desk." Identify the cause for this error message. (Choose the best answer.)

정답: C
설명: (KoreaDumps 회원만 볼 수 있음)
문제8
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)

정답: A
설명: (KoreaDumps 회원만 볼 수 있음)
문제9
Your organization has created an Enterprise Project Structure (EPS) and your executives review the overall project labor demand by using the EPS. Identify two correct statements about the periodic project labor demand. (Choose two.)

정답: A,B
설명: (KoreaDumps 회원만 볼 수 있음)
문제10
While creating a new project template, you notice that a default Asset Cost Allocation method is being automatically associated. Identify the source setup from which the default value is being inherited. (Choose the best answer.)

정답: C
설명: (KoreaDumps 회원만 볼 수 있음)

KoreaDumps의 제품으로 GO GO GO !

자격증의 중요성:

경쟁율이 심한 IT시대에 인증시험을 패스함으로 IT업계 관련 직종에 종사하고자 하는 분들에게는 아주 큰 가산점이 될수 있고 자신만의 위치를 보장할수 있으며 더욱이는 한층 업된 삶을 누릴수 있을수도 있습니다.

KoreaDumps 제품의 가치:

KoreaDumps에는 IT인증시험의 최신 학습가이드가 있습니다. KoreaDumps의 IT전문가들이 자신만의 경험과 끊임없는 노력으로 최고의 학습자료를 작성해 여러분들이 시험에서 패스하도록 도와드립니다.

무료샘플 받아보기:

관심있는 인증시험과목 덤프의 무료샘플을 원하신다면 덤프구매사이트의 PDF Version Demo 버튼을 클릭하고 메일주소를 입력하시면 바로 다운받아 덤프의 일부분 문제를 체험해 보실수 있습니다.

완벽한 서비스 제공:

KoreaDumps는 한국어로 온라인상담과 메일상담을 받습니다. 덤프구매후 일년동안 무료 업데이트 서비스를 제공해드리며 구매일로 부터 60일내에 시험에서 떨어지는 경우 덤프비용 전액을 환불해드려 고객님의 부담을 덜어드립니다.