최신Oracle Project Management Cloud 2025 Implementation Professional - 1z0-1057-25무료샘플문제
문제1
Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this. (Choose the best answer.)
Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this. (Choose the best answer.)
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)
문제2
Your organization has decided to enable the common accounting and project accounting periods option while defining business unit implementation options.
Where will you maintain the accounting period statuses if this option has been enabled?
Your organization has decided to enable the common accounting and project accounting periods option while defining business unit implementation options.
Where will you maintain the accounting period statuses if this option has been enabled?
정답: B
문제3
When scheduling the Update Project Performance Data process to run on a periodic basis, which summarization method would you select? (Choose the best answer.)
When scheduling the Update Project Performance Data process to run on a periodic basis, which summarization method would you select? (Choose the best answer.)
정답: A
설명: (KoreaDumps 회원만 볼 수 있음)
문제4
You are trying to create a project purchase order (PO) but you are unable to select Expenditure Organization in the PO. Identify two reasons for this problem. (Choose two.)
You are trying to create a project purchase order (PO) but you are unable to select Expenditure Organization in the PO. Identify two reasons for this problem. (Choose two.)
정답: B,D
설명: (KoreaDumps 회원만 볼 수 있음)
문제5
You have a billable project for which the following details are provided:
Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
Associated Project Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)
You have a billable project for which the following details are provided:
Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
Associated Project Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)
문제6
You have four resources in your organization: P, Q, R, and S.
Resource P - Project or resource calendar is active.
Resource Q - Project resource request dates are within the project or resource calendar effective dates.
Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)
You have four resources in your organization: P, Q, R, and S.
Resource P - Project or resource calendar is active.
Resource Q - Project resource request dates are within the project or resource calendar effective dates.
Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)
문제7
Identify the three contract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)
Identify the three contract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)
정답: B,C,E
설명: (KoreaDumps 회원만 볼 수 있음)
문제8
You have defined two expenditure types but they are not available for selection when you enter an expenditure batch.
What is the reason for this problem?
You have defined two expenditure types but they are not available for selection when you enter an expenditure batch.
What is the reason for this problem?
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)
문제9
A consulting services company is currently working on a business transformation project for your client, which spans multiple years. At the first period close, the consulting services company has recognized revenue and the accounting entry created is:
Dr Unbilled Receivables 40,000
Cr Revenue 40,000
At the end of the period, the client is sent an associated bill. What would be the corresponding invoice accounting entry? (Choose the best answer.)
A consulting services company is currently working on a business transformation project for your client, which spans multiple years. At the first period close, the consulting services company has recognized revenue and the accounting entry created is:
Dr Unbilled Receivables 40,000
Cr Revenue 40,000
At the end of the period, the client is sent an associated bill. What would be the corresponding invoice accounting entry? (Choose the best answer.)
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)