최신GAQM Associate in Project Management (APM) - APM-001무료샘플문제
문제1
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
정답: A
문제2
The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:
The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:
정답: A
문제3
Which of the following reduces the probability of potential consequences of project risk events?
Which of the following reduces the probability of potential consequences of project risk events?
정답: C
문제4
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
정답: C
문제5
Which of the following is an input to Develop Human Resource Plan?
Which of the following is an input to Develop Human Resource Plan?
정답: C
문제6
In which process is a project manager identified and given the authority to apply resources to project activities?
In which process is a project manager identified and given the authority to apply resources to project activities?
정답: B
문제7
Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?
Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?
정답: C
문제8
The purpose of inspection in Perform Quality Control is to keep errors:
The purpose of inspection in Perform Quality Control is to keep errors:
정답: B
문제9
The definition of operations is a/an:
The definition of operations is a/an:
정답: C
문제10
Which tool or technique is used in validating the scope of a project?
Which tool or technique is used in validating the scope of a project?
정답: A
문제11
Which input will be used when tasked with developing the human resource plan?
Which input will be used when tasked with developing the human resource plan?
정답: B