최신APM Project Fundamentals Qualification (PFQ) - APM-PFQ무료샘플문제
문제1
The process that evaluates overall project performance to provide confidence is called:
The process that evaluates overall project performance to provide confidence is called:
정답: C
문제2
Which one of the following best describes project sponsorship?
Which one of the following best describes project sponsorship?
정답: D
문제3
To be considered effective. how should quality management be used in the project?
To be considered effective. how should quality management be used in the project?
정답: B
문제4
Which of these is not part of the linear project life cycle?
Which of these is not part of the linear project life cycle?
정답: D
문제5
Once a change has been requested what is the next step in the change control process?
Once a change has been requested what is the next step in the change control process?
정답: D
문제6
One aspect of quality planning is to:
One aspect of quality planning is to:
정답: A
문제7
What role does the project manager have in the writing of the business case? The project manager:
What role does the project manager have in the writing of the business case? The project manager:
정답: C
문제8
Understanding who stakeholders are and their needs is a key duty of
Understanding who stakeholders are and their needs is a key duty of
정답: D
문제9
A review most closely linked to the phases Of the project life cycle could be described as a:
A review most closely linked to the phases Of the project life cycle could be described as a:
정답: A
문제10
What is the main reason for an initial high-level review of a change request?
What is the main reason for an initial high-level review of a change request?
정답: D
문제11
Which of the following estimating techniques utilizes work packages, assigning costs and consolidating to provide a project estimate?
Which of the following estimating techniques utilizes work packages, assigning costs and consolidating to provide a project estimate?
정답: C
문제12
Cost Breakdown Structure (CBS) shows costs assigned to:
Cost Breakdown Structure (CBS) shows costs assigned to:
정답: C
문제13
Which of the following BEST describes a project issue?
Which of the following BEST describes a project issue?
정답: B