문제1
The business analyst (BA) is assigned a small project, requiring minor enhancements to an existing system. The BA will meet with the business sponsor and developer next week to gather information about the change. What should the BA review before the meeting?
The business analyst (BA) is assigned a small project, requiring minor enhancements to an existing system. The BA will meet with the business sponsor and developer next week to gather information about the change. What should the BA review before the meeting?
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)
문제2
You are a business analyst for your organization. Your current business analysis endeavor includes working with stakeholders who are located in offices around the world. Because these stakeholders are dispersed, what are likely to increase in this endeavor as opposed to a collocated group of stakeholders?
You are a business analyst for your organization. Your current business analysis endeavor includes working with stakeholders who are located in offices around the world. Because these stakeholders are dispersed, what are likely to increase in this endeavor as opposed to a collocated group of stakeholders?
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)
문제3
A general insurance company wants to enter a new market that has the potential for high profit and little competition. The business analyst (BA) was asked to prepare a presentation for key stakeholders to show how the new segment will deliver value for stakeholders. Which of the following is best suited for this purpose?
A general insurance company wants to enter a new market that has the potential for high profit and little competition. The business analyst (BA) was asked to prepare a presentation for key stakeholders to show how the new segment will deliver value for stakeholders. Which of the following is best suited for this purpose?
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)
문제4
You are a Business Analyst for your organization, and you're preparing to elicit requirements from stakeholders. You've gathered several inputs to help with the elicitation process. Which input will you use to ensure that you understand the type of information that should be elicited from stakeholders?
You are a Business Analyst for your organization, and you're preparing to elicit requirements from stakeholders. You've gathered several inputs to help with the elicitation process. Which input will you use to ensure that you understand the type of information that should be elicited from stakeholders?
정답: D
설명: (KoreaDumps 회원만 볼 수 있음)
문제5
Which of the following defines all of the features and functions of the thing, solution, or service the project or organization will create?
Which of the following defines all of the features and functions of the thing, solution, or service the project or organization will create?
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)
문제6
Which of the following defines all of the required work to satisfy the requirements of the project?
Which of the following defines all of the required work to satisfy the requirements of the project?
정답: A
설명: (KoreaDumps 회원만 볼 수 있음)
문제7
A global organization is implementing a new Knowledge Management System, and communication to the different regions has been informal. The approach is to convert the few remaining regions iteratively. The team has experienced variances at this point but feels confident in these final conversions. How should the business analyst (BA) communicate the information?
A global organization is implementing a new Knowledge Management System, and communication to the different regions has been informal. The approach is to convert the few remaining regions iteratively. The team has experienced variances at this point but feels confident in these final conversions. How should the business analyst (BA) communicate the information?
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)
문제8
You have identified a task in your task list that cannot be completed until the inspector for the project signs off on the initial deliverables. The inspector's signoff on the initial deliverables is called what?
You have identified a task in your task list that cannot be completed until the inspector for the project signs off on the initial deliverables. The inspector's signoff on the initial deliverables is called what?
정답: D
설명: (KoreaDumps 회원만 볼 수 있음)
문제9
A business analyst (BA) has completed multiple workshops involving a number of stakeholders, including the project manager; however, the elicitation results are inconsistent between the stakeholders. How should the variation in results be resolved?
A business analyst (BA) has completed multiple workshops involving a number of stakeholders, including the project manager; however, the elicitation results are inconsistent between the stakeholders. How should the variation in results be resolved?
정답: D
설명: (KoreaDumps 회원만 볼 수 있음)
문제10
You are a business analyst for your organization and you're working with Mary. Mary wants to know what you need to complete the process of planning the business analysis approach if you're already the business analyst for your organization. This approach helps to find out the following except for which one?
You are a business analyst for your organization and you're working with Mary. Mary wants to know what you need to complete the process of planning the business analysis approach if you're already the business analyst for your organization. This approach helps to find out the following except for which one?
정답: A
설명: (KoreaDumps 회원만 볼 수 있음)
문제11
There are three inputs in the plan business analysis approach. Which one of the following is not one of the three inputs?
There are three inputs in the plan business analysis approach. Which one of the following is not one of the three inputs?
정답: A