문제1
Which of the following elements does MRP take into account during net requirement calculation?
Note: There are 2 correct answers to this question.
Which of the following elements does MRP take into account during net requirement calculation?
Note: There are 2 correct answers to this question.
정답: C,D
문제2
Which planning strategies can you use in the capacity scheduling table?
Note: There are 2 correct answers to this question.
Which planning strategies can you use in the capacity scheduling table?
Note: There are 2 correct answers to this question.
정답: A,C
문제3
What is the focus of repetitive manufacturing?
What is the focus of repetitive manufacturing?
정답: B
문제4
Which of the following processes lead to an indicator in the planning file?
Note: There are 2 correct answers to this question.
Which of the following processes lead to an indicator in the planning file?
Note: There are 2 correct answers to this question.
정답: A,C
문제5
During production order creation, several valid production versions are found.
How does the system choose the production version?
During production order creation, several valid production versions are found.
How does the system choose the production version?
정답: A
문제6
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
Note: There are 2 correct answers to this question.
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
Note: There are 2 correct answers to this question.
정답: C,D
문제7
What is a prerequisite for the consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?
What is a prerequisite for the consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?
정답: A
문제8
Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.
Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.
정답: A,C
문제9
Which options do you have to post goods receipt for a process order?
Note: There are 2 correct answers to this question.
Which options do you have to post goods receipt for a process order?
Note: There are 2 correct answers to this question.
정답: B,D