문제1
What tasks are performed by the system during activity allocation? There are TWO correct answers for this question
What tasks are performed by the system during activity allocation? There are TWO correct answers for this question
정답: A,D
문제2
You want to define requirement levels for users for the authorization check in Profitability Analysis reporting.
Whichrequirement level would you set to enable user access to all the interactive drill down functions?
You want to define requirement levels for users for the authorization check in Profitability Analysis reporting.
Whichrequirement level would you set to enable user access to all the interactive drill down functions?
정답: B
문제3
What parameters can ou se up when defining order types?
What parameters can ou se up when defining order types?
정답: A,C
문제4
When you create a profit center, what company code(s) is it assigned to by default ?
When you create a profit center, what company code(s) is it assigned to by default ?
정답: A
문제5
Which are mandatory attributes, when you create an operating concern with costing-based and account-based CO-PA? There are TWO correct answers for this question
Which are mandatory attributes, when you create an operating concern with costing-based and account-based CO-PA? There are TWO correct answers for this question
정답: B,C
문제6
Which of the following steps are part of the procedure to update the standard price of the material ? 2 answers
Which of the following steps are part of the procedure to update the standard price of the material ? 2 answers
정답: A,B
문제7
Which activity do you perform during period-end in profit center accounting?
Which activity do you perform during period-end in profit center accounting?
정답: B
문제8
You want to creat cost centers for you company. What is the prerequisite to building an organizational structure for overhead cost controlling?
You want to creat cost centers for you company. What is the prerequisite to building an organizational structure for overhead cost controlling?
정답: C
문제9
You post an expense line in an accounting document and enter an internal order and a cost center as the account assignments. After posting, the system allows you to settle the posted values from the internal order.
Which settings do the cost center and internal order have?
You post an expense line in an accounting document and enter an internal order and a cost center as the account assignments. After posting, the system allows you to settle the posted values from the internal order.
Which settings do the cost center and internal order have?
정답: B
문제10
You need to analyzedifferent planning scenarios for cost centers. With which object do you differentiate the planning scenarios?
You need to analyzedifferent planning scenarios for cost centers. With which object do you differentiate the planning scenarios?
정답: B
문제11
you want to set up integrated planning for your internal orders. What do you need to do ? 2 Answers
you want to set up integrated planning for your internal orders. What do you need to do ? 2 Answers
정답: B,C