최신Peoplecert PRINCE2 Foundation - PC0-004무료샘플문제
문제1
Which of the following is NOT part of quality control?
Which of the following is NOT part of quality control?
정답: D
문제2
What product forms the contract' between the Project Board and the Project Manager?
What product forms the contract' between the Project Board and the Project Manager?
정답: D
문제3
Which process provides the Project Board with the information it requires in order to commit
resources to the project?
Which process provides the Project Board with the information it requires in order to commit
resources to the project?
정답: B
문제4
Who does the Team Manager report to and take direction from?
Who does the Team Manager report to and take direction from?
정답: C
문제5
Which is a responsibility of a risk owner?
Which is a responsibility of a risk owner?
정답: A
문제6
Which is a purpose of the Quality theme?
Which is a purpose of the Quality theme?
정답: C
문제7
Why would the Project Manager escalate an issue to the Project Board?
Why would the Project Manager escalate an issue to the Project Board?
정답: A
문제8
When considering how long the project stages should be, which might be a reason for one stage to be longer than others?
When considering how long the project stages should be, which might be a reason for one stage to be longer than others?
정답: A
문제9
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
정답: A
문제10
Which is a purpose of the Organization theme?
Which is a purpose of the Organization theme?
정답: D
문제11
Which should be funded from a change budget?
Which should be funded from a change budget?
정답: B
문제12
Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?
Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?
정답: D
문제13
Which role is part of the project management team?
Which role is part of the project management team?
정답: B
문제14
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
정답: A
문제15
Which is part of quality control?
Which is part of quality control?
정답: C