문제1
What is one benefit of documenting the change control process?
What is one benefit of documenting the change control process?
정답: A
설명: (KoreaDumps 회원만 볼 수 있음)
문제2
A business analyst is working on a project to update the user interface for a legacy procurement system. An end user raises concerns that the new solution will not support their core business processes.
How could the business analyst address the end user's concerns about the new interface?
A business analyst is working on a project to update the user interface for a legacy procurement system. An end user raises concerns that the new solution will not support their core business processes.
How could the business analyst address the end user's concerns about the new interface?
정답: A
설명: (KoreaDumps 회원만 볼 수 있음)
문제3
What is a standardized, effective, and efficient way to manage changes to project documentation?
What is a standardized, effective, and efficient way to manage changes to project documentation?
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)
문제4
Company A has been awarded a contract to finalize the development of a product that Company B was not able to finish. The business analyst is given a copy of the documentation left by Company B.
To which of the following documents should the business analyst pay the most attention to ensure the project succeeds this time?
Company A has been awarded a contract to finalize the development of a product that Company B was not able to finish. The business analyst is given a copy of the documentation left by Company B.
To which of the following documents should the business analyst pay the most attention to ensure the project succeeds this time?
정답: D
설명: (KoreaDumps 회원만 볼 수 있음)
문제5
The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs.
Which project artifact could the test team review to help identify acceptance criteria?
The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs.
Which project artifact could the test team review to help identify acceptance criteria?
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)
문제6
Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?
Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)
문제7
When eliciting requirements, a good time to consider using the interviewing method is when:
When eliciting requirements, a good time to consider using the interviewing method is when:
정답: A
설명: (KoreaDumps 회원만 볼 수 있음)
문제8
What are some of the components of a requirements management plan?
What are some of the components of a requirements management plan?
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)
문제9
In order to reduce product and project risk for a large, complex project, a business analyst is asked to help develop a change process that includes formal authorization and tracking throughout the life cycle of the project. The business analyst needs a capability that will help ensure that the product conforms to approved requirements, changes can be documented, and the status of each change can be reported.
What should the business analyst use?
In order to reduce product and project risk for a large, complex project, a business analyst is asked to help develop a change process that includes formal authorization and tracking throughout the life cycle of the project. The business analyst needs a capability that will help ensure that the product conforms to approved requirements, changes can be documented, and the status of each change can be reported.
What should the business analyst use?
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)
문제10
During validation of a project solution, the business analyst discovers that a requirement has been altered.
Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.
Which corrective action should the business analyst take?
During validation of a project solution, the business analyst discovers that a requirement has been altered.
Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.
Which corrective action should the business analyst take?
정답: A
설명: (KoreaDumps 회원만 볼 수 있음)