문제1
You are the project manager of the AHQ project. This project is scheduled to last for six months and will require S345.000 to complete. If the project completes earlier than scheduled your organization will receive a bonus of S5 000 per day of early completion Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?
You are the project manager of the AHQ project. This project is scheduled to last for six months and will require S345.000 to complete. If the project completes earlier than scheduled your organization will receive a bonus of S5 000 per day of early completion Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?
정답: A
문제2
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)
문제3
What problems can a soils engineer deal with on a project?
What problems can a soils engineer deal with on a project?
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)
문제4
Who can define KPls?
Who can define KPls?
정답: C
문제5
Before the work begins, the contractor considers crashing the schedule. How much would the crashed general conditions have to be reduced to break even with the normal cost budget?

Before the work begins, the contractor considers crashing the schedule. How much would the crashed general conditions have to be reduced to break even with the normal cost budget?

정답: A
문제6
During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?
During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?
정답: D
설명: (KoreaDumps 회원만 볼 수 있음)
문제7
In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?
In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)
문제8
What is a critical path method schedule?
What is a critical path method schedule?
정답: A
설명: (KoreaDumps 회원만 볼 수 있음)
문제9
An earned value-based project control system can use either of which two budgets as the basis of its calculations?
An earned value-based project control system can use either of which two budgets as the basis of its calculations?
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)