문제1
Which preliminary deliverables are usually provided for a schematic phase submission? Check the four that apply.
Which preliminary deliverables are usually provided for a schematic phase submission? Check the four that apply.
정답: A,D,E,F
설명: (KoreaDumps 회원만 볼 수 있음)
문제2
Which project delivery method allows the owner to engage the architect, contractor, and key consultants in a single collaborative contract?
Which project delivery method allows the owner to engage the architect, contractor, and key consultants in a single collaborative contract?
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)
문제3
A contractor has hired a subcontractor to construct a parking lot for 60 cars. The parking lot will be 60 feet x
270 feet. The subcontractor has quoted a price of $13.25 per square yard to the contractor.
If the contractor adds a mark-up of 15%, what is the cost of each parking space?
A contractor has hired a subcontractor to construct a parking lot for 60 cars. The parking lot will be 60 feet x
270 feet. The subcontractor has quoted a price of $13.25 per square yard to the contractor.
If the contractor adds a mark-up of 15%, what is the cost of each parking space?
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)
문제4
Preparation of space standards, furniture assessment, and documentation of equipment requirements are most effectively done during which of the following project phases?
Preparation of space standards, furniture assessment, and documentation of equipment requirements are most effectively done during which of the following project phases?
정답: A
설명: (KoreaDumps 회원만 볼 수 있음)
문제5
What is the architect's primary responsibility when responding to a contractor's Request for Information (RFI) during construction?
What is the architect's primary responsibility when responding to a contractor's Request for Information (RFI) during construction?
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)
문제6
Construction of a gymnasium is scheduled to be complete 365 days from the date of the notice to proceed. On Friday, day 355 of the schedule, the contractor submits a punch list to the architect for substantial completion.
The architect agrees to review the punch list on-site after the weekend.
On Monday, the architect discovers that a subcontractor left open a skylight over the weekend, allowing heavy rain to fall into the courtyard area and damage the gymnasium floor. It was determined the flooring must be replaced. The lead time for new flooring is 8-10 weeks, and installation will take 14 days. The architect's agreement with the owner is contracted to end 30 days after substantial completion.
Which of the following documents must the architect prepare immediately? Check the two that apply.
Construction of a gymnasium is scheduled to be complete 365 days from the date of the notice to proceed. On Friday, day 355 of the schedule, the contractor submits a punch list to the architect for substantial completion.
The architect agrees to review the punch list on-site after the weekend.
On Monday, the architect discovers that a subcontractor left open a skylight over the weekend, allowing heavy rain to fall into the courtyard area and damage the gymnasium floor. It was determined the flooring must be replaced. The lead time for new flooring is 8-10 weeks, and installation will take 14 days. The architect's agreement with the owner is contracted to end 30 days after substantial completion.
Which of the following documents must the architect prepare immediately? Check the two that apply.
정답: B,F
설명: (KoreaDumps 회원만 볼 수 있음)
문제7

Design Firm ABC is awarded two projects, but they do not have enough staff to support the execution of both projects due to unexpected staffing issues. ABC is deciding if they need to hire staff from an outside firm to execute the projects.
Which one of the following sets of staff members would adequately support ABC's staffing needs?

Design Firm ABC is awarded two projects, but they do not have enough staff to support the execution of both projects due to unexpected staffing issues. ABC is deciding if they need to hire staff from an outside firm to execute the projects.
Which one of the following sets of staff members would adequately support ABC's staffing needs?
정답: C
설명: (KoreaDumps 회원만 볼 수 있음)
문제8
The Integrated Project Delivery (IPD) method is used for a new football stadium project in an urban downtown area. After completing 60% implementation documents, the owner requests a digital scoreboard that is 20% larger than previously specified. The architect is concerned that the larger scoreboard will exceed the height limitations dictated by the city. The IPD team will conduct a constructability review and evaluate the modification of the scoreboard. Including the architect, which members of the IPD team are required to participate in the constructability review?
The Integrated Project Delivery (IPD) method is used for a new football stadium project in an urban downtown area. After completing 60% implementation documents, the owner requests a digital scoreboard that is 20% larger than previously specified. The architect is concerned that the larger scoreboard will exceed the height limitations dictated by the city. The IPD team will conduct a constructability review and evaluate the modification of the scoreboard. Including the architect, which members of the IPD team are required to participate in the constructability review?
정답: B
설명: (KoreaDumps 회원만 볼 수 있음)