문제1
A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list During the final review of the RFPs the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest.
What should the program manager do?
A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list During the final review of the RFPs the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest.
What should the program manager do?
정답: B
문제2
Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule What should the program manager do?
Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule What should the program manager do?
정답: B
문제3
A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder'?
A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder'?
정답: D
문제4
The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system's cost. The program manager has provided monthly performance reports throughout the program's lite cycle.
Which of the following would the customer be interested in reviewing?
The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system's cost. The program manager has provided monthly performance reports throughout the program's lite cycle.
Which of the following would the customer be interested in reviewing?
정답: A
문제5
An organization is embarking on a new program aligned with its strategic objectives The new program has a High level of risk due to the rapidly changing technical landscape in which the organization operates The organization has mature program management capabilities, as measured by its resources, intellectual assets, and management processes.
Given the organization's history of delivering successful programs, what should the program manager do as part of the planning process?
An organization is embarking on a new program aligned with its strategic objectives The new program has a High level of risk due to the rapidly changing technical landscape in which the organization operates The organization has mature program management capabilities, as measured by its resources, intellectual assets, and management processes.
Given the organization's history of delivering successful programs, what should the program manager do as part of the planning process?
정답: A
문제6
A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals A materials supplier informs the program manager that when this agreement is finalized, it will shorten the products delivery time.
What should the program manager update first?
A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals A materials supplier informs the program manager that when this agreement is finalized, it will shorten the products delivery time.
What should the program manager update first?
정답: A
문제7
When should a program manager approve the closure of a component project?
When should a program manager approve the closure of a component project?
정답: C
문제8
In a budding with one join room for serving as the FR and EF and four dedicated TRs on the same floor a total of__________ 103 mm (4 trade size) conduits should be installed to interconnect the backbone pathways to the ER.
In a budding with one join room for serving as the FR and EF and four dedicated TRs on the same floor a total of__________ 103 mm (4 trade size) conduits should be installed to interconnect the backbone pathways to the ER.
정답: D
문제9
A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement What should the program manager do first?
A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement What should the program manager do first?
정답: D