문제1
A set of requirements for a new retail app has been prioritised using MoSCoW as follows:
REQ#1: (S)
REQ#2: (C)
REQ#3: (S)
REQ#4: (M)
REQ#5: (M)
REQ#6: (C)
REQ#7: (W)
All M, S and C. requirements have been approved for inclusion in the first iteration of the project.
Which of these requirements constitute the minimum usable subset of the first iteration?
A set of requirements for a new retail app has been prioritised using MoSCoW as follows:
REQ#1: (S)
REQ#2: (C)
REQ#3: (S)
REQ#4: (M)
REQ#5: (M)
REQ#6: (C)
REQ#7: (W)
All M, S and C. requirements have been approved for inclusion in the first iteration of the project.
Which of these requirements constitute the minimum usable subset of the first iteration?
정답: B
문제2
The following have been extracted from the requirements list for a component manufacturing machine:
R#1.1 The system must inform the user of a misplaced component by sounding an audible alarm.
R#1.2 The system must be able to be serviced within the 8 hour overnight shut down period.
How will these requirements be categorised?
The following have been extracted from the requirements list for a component manufacturing machine:
R#1.1 The system must inform the user of a misplaced component by sounding an audible alarm.
R#1.2 The system must be able to be serviced within the 8 hour overnight shut down period.
How will these requirements be categorised?
정답: C
문제3
A business analyst is categorizing requirements in a requirements catalogue.
Which of the following would be classed as a non-functional requirement?
A business analyst is categorizing requirements in a requirements catalogue.
Which of the following would be classed as a non-functional requirement?
정답: C
문제4
A car manufacturer wishes to understand what customers want from its cars. Consequently, it has invited one hundred customers to a series of meetings, where they will explore new technology and generate ideas for future developments and directions.
The outcomes of these meetings will be considered by the team responsible for new car development.
Which requirements elicitation technique is going to be used?
A car manufacturer wishes to understand what customers want from its cars. Consequently, it has invited one hundred customers to a series of meetings, where they will explore new technology and generate ideas for future developments and directions.
The outcomes of these meetings will be considered by the team responsible for new car development.
Which requirements elicitation technique is going to be used?
정답: C
문제5
Peter is analyzing requirements elicited for a sales order system. He is looking at the following requirement to see if it is fit for purpose:
'The system shall calculate the total volume of orders received per salesman on Fridays, except when the end of year reports are being run'.
During requirements analysis, requirements are checked for:
(A) Ambiguity.
(B) Relevance.
(C) Clarity.
(D) Whether the requirement is a solution.
On which of these checks would this requirement fail?
Peter is analyzing requirements elicited for a sales order system. He is looking at the following requirement to see if it is fit for purpose:
'The system shall calculate the total volume of orders received per salesman on Fridays, except when the end of year reports are being run'.
During requirements analysis, requirements are checked for:
(A) Ambiguity.
(B) Relevance.
(C) Clarity.
(D) Whether the requirement is a solution.
On which of these checks would this requirement fail?
정답: A
문제6
Kings Castle Travel organises UK walking tours and has begun a programme to upgrade its IT systems. Its Walks System will hold details of all the walking routes the company uses to create its tour packages. These routes are designed and written by the walking guides and are currently held in spreadsheet files on the office computer.
The functionality of the new system will include the ability to import walking routes from these spreadsheets. All routes held on the system will be checked by the walking guides and authorised for use by the tour manager.
What will NOT be an actor on the use case diagram?
Kings Castle Travel organises UK walking tours and has begun a programme to upgrade its IT systems. Its Walks System will hold details of all the walking routes the company uses to create its tour packages. These routes are designed and written by the walking guides and are currently held in spreadsheet files on the office computer.
The functionality of the new system will include the ability to import walking routes from these spreadsheets. All routes held on the system will be checked by the walking guides and authorised for use by the tour manager.
What will NOT be an actor on the use case diagram?
정답: B
문제7
A developer working to implement a set of baselined requirements has called the business analyst responsible for the project to check her understanding of a key requirement. During the conversation, it becomes clear to both parties that the developer is working on an older version of the requirement.
Which element of requirements management has failed?
A developer working to implement a set of baselined requirements has called the business analyst responsible for the project to check her understanding of a key requirement. During the conversation, it becomes clear to both parties that the developer is working on an older version of the requirement.
Which element of requirements management has failed?
정답: A
문제8
Isamu is a business analyst working on a project. Unfortunately, it is not progressing as hoped or planned.
He has identified that the main issues with the users on the project are:
1) They manage complex processes and they do not seem to be able to
articulate their needs.
2) They claim they cannot engage in requirements elicitation as they
simply do not know what is possible.
Which elicitation technique would best address both these issues?
Isamu is a business analyst working on a project. Unfortunately, it is not progressing as hoped or planned.
He has identified that the main issues with the users on the project are:
1) They manage complex processes and they do not seem to be able to
articulate their needs.
2) They claim they cannot engage in requirements elicitation as they
simply do not know what is possible.
Which elicitation technique would best address both these issues?
정답: C